Single beam gantry crane installation project 1. Before installing the gantry crane, all ground anchors must be inspected and accepted. Installation can only be carried out after passing the inspection. 2. Select two qualified truck cranes for installation according to the installation requirements of the single beam gantry crane manufacturer.
Gantry crane installation acceptance and process safety management Sevencrane single beam gantry crane factory installation acceptance: 1. Before installation: Whether the installation qualifications and installation plan comply with the installer’s certificate, and whether the ID card matches the installer’s safety education and disclosure. 2. Installation process: The installation process is monitored, and a dedicated person stands by to supervise the installation personnel with regular safety education and explanations. Organize and carry out special safety inspections for installation. 3. Installation is completed: organizers, acceptance personnel, and acceptance units arrive at the site for on-site acceptance. The safety device shall be inspected and accepted through trial operation. 4. Trial operation: Operators and commanders must hold certificates to work, and check whether the certificates match. Safety education and briefing for operators and commanders. 5. Safety device acceptance.
Gantry crane safety control visualization 1. Site closure and warning for hoisting operations. 2. Big hook safety warning color. 3. Visualization of limits such as iron shoes, rail clamps, and infrared sensors. 4. Big hook ground anchor visualization.
5. Set retaining rings on the upper and lower ladder passages and hang anti-fall devices. 6. Special operation personnel must hold a certificate to work, and an acceptance sign should be displayed in a conspicuous position on the machinery. 7. The ground endurance when installing the track should meet the requirements. The spacing between track joints should be ≤4mm, the height difference between the joints should be ≤2mm, and lightning protection jumpers should be installed at the joints.
Wireless remote control single beam gantry crane company disassembly and exit Preparations before dismantling the gantry crane: 1. Set up disassembly notices for gantry cranes, remove surrounding debris, and set up cordons; 2. Select a qualified truck crane to cooperate with the disassembly according to the disassembly requirements (operators must hold certificates to work); 3. The spreaders, equipment and ground anchors used must be checked and calculated, and they can only be used if they pass the test; 4. Provide disassembly safety technical explanations, safety education and training, and arrange for dedicated personnel to supervise the whole process; 5. Turn off the power before disassembly and lower the hook of best single beam gantry crane for sale.
Disassembly sequence: 1. Electrical disassembly; 2. Disassembly of ancillary facilities; 3. Disassembly of the driver’s cab; 4. Disassembly of the trolley; 5. Disassembly of the main beam; 6. Disassembly of the outriggers; 7. Disassembly of the track trolley; 8. Clean up and exit.
This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.
Strictly Necessary Cookies
Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.
If you disable this cookie, we will not be able to save your preferences. This means that every time you visit this website you will need to enable or disable cookies again.